RBSC

Collapse

Announcement

Collapse
No announcement yet.

Corruption at Garvey Maceo School?

Collapse
X
 
  • Filter
  • Time
  • Show
Clear All
new posts

  • Corruption at Garvey Maceo School?

    $Multimillion Mystery - Auditors Called In Six Years After School Spends More Than $40 Million On A Yet-To-Be Delivered Three-Storey Block
    Published: Sunday | April 21, 2013 7 Comments

    Erica Virtue, Senior Gleaner Writer

    More than $40 million has been spent to construct a three-storey classroom block at the Garvey Maceo High School in Clarendon, but six years later all the school has to show for the money is a partially done two-storey structure, and no one, it seems, can explain where the money went.

    Four principals, two contractors, two audits, and nearly a million dollars more over budget later, a completion date for the building remains a mystery.

    Any explanation of how the money was spent would have to come from the two contractors who worked on the project, but efforts by The Sunday Gleaner to contact them have, so far, been unsuccessful.

    However, persons close to the school say there were close ties between school officials and one former contractor, while a former board member was at one time the main contractor, and equipment belonging to a school official was used on the project.

    Read more: http://jamaica-gleaner.com/gleaner/2...ead/lead1.html


    BLACK LIVES MATTER

  • #2
    How to do it on time and within budget

    Originally posted by Mosiah View Post
    $Multimillion Mystery - Auditors Called In Six Years After School Spends More Than $40 Million On A Yet-To-Be Delivered Three-Storey Block
    Published: Sunday | April 21, 2013 7 Comments

    Erica Virtue, Senior Gleaner Writer

    More than $40 million has been spent to construct a three-storey classroom block at the Garvey Maceo High School in Clarendon, but six years later all the school has to show for the money is a partially done two-storey structure, and no one, it seems, can explain where the money went.

    Four principals, two contractors, two audits, and nearly a million dollars more over budget later, a completion date for the building remains a mystery.

    Any explanation of how the money was spent would have to come from the two contractors who worked on the project, but efforts by The Sunday Gleaner to contact them have, so far, been unsuccessful.

    However, persons close to the school say there were close ties between school officials and one former contractor, while a former board member was at one time the main contractor, and equipment belonging to a school official was used on the project.

    Read more: http://jamaica-gleaner.com/gleaner/2...ead/lead1.html

    Kemps did it - Educators enforce strict rules for on-budget, on-time construction of three-storey block

    Published: Sunday | April 21, 2013 2 Comments


    The man in whose honour the new building is named at Kemps Hill High, former principal Lebert C. Wright, demonstrating his caring side to these students in a 2011 photo. - File



    The completed L.C. Wright block at Kemps Hill High School in Clarendon. - Photo by Ian Allen/Photographer



    Kemps Hill High School's guidance counsellor, Delores Miller, takes her young charges through a session on deportment during a recent observation of girls' day. - - Photo by Ian Allen/Photographer




    1 2 3 >

    Erica Virtue, Senior Gleaner WriterLocated in the sugar-cane belt in Clarendon, Kemps Hill High School sits on nine and a half acres of land in one of the poorest areas in the island. However, the clean environment of the school and the interior and exterior beauty would cause several prominent high schools across the island to be envious.
    Principal Rohan Copeland and his vice-principal, Vernon Morrison, said the school and the children were the country's [COLOR=blue !important][COLOR=blue !important]investment[/COLOR][/COLOR], with the teachers and administrators mere custodians of the nation's trust.
    Two years ago, the school completed the construction of the L.C. Wright building, which is named in honour of a former principal.
    The majority of funding for the new building came from the [COLOR=blue !important][COLOR=blue !important]education[/COLOR][/COLOR] ministry, but Copeland says the school contributed nearly $10 million towards the building of the three-storey block.
    The school's contribution came from [COLOR=blue !important][COLOR=blue !important]fundraising[/COLOR][/COLOR] activities as well as its tuck shop savings.
    "I don't know how the contractor was chosen because I was not the principal then. But I can tell you that we - myself and the vice-principal - were vigilant like hawks, especially because we were [COLOR=blue !important][COLOR=blue !important]investing[/COLOR][/COLOR] our hard-earned savings, and we were also cognisant that we were in charge of taxpayers' money," Copeland said,
    "If the contractor was given 40 bags of cement today and at the end of the day he said he used 23, we asked for the used bags and counted the 23 used bags. We made sure that the 17 unused bags were locked away for usage the next day. We did not let up; we were vigilant to the day it was finished," said Morrison, as the two spoke with The Sunday Gleaner last week.
    Everything accounted for
    Copeland said the school can [COLOR=blue !important][COLOR=blue !important]account[/COLOR][/COLOR] "for every inch of steel that was used anywhere on the building".
    According to the principal, personnel from the Ministry of Education gave technical assistance from the start to the finish of the project.
    When the project was fully completed in January 2011, there were three completed blocks, comprising 11 classrooms, a male and female bathroom, a storeroom and two offices.
    The first two floors were completed in 2009, and the third floor just over a year later.
    "The block now houses about 500 fourth- and fifth-form students. When it was completed, it was handed over with light, water, completed bathrooms and it was painted. The keys were given to us and once we furnished it, it was ready for use," said Copeland.
    "The money for the total project was not handed over at once, but in tranches, and only after officials of the ministry came in, did their inspection and signed off the work. Essentially, the payments were incremental."
    Copeland and Morrison started at Kemps Hill in 1993, fresh out of teachers' college, and have seen the school's population double and its physical size increase.
    "The school population has increased and so has the teaching population. However, the support staff has remained the same, so there is a lot of pressure, but we manage. The school is an investment to the community," said Copeland.
    He praised the community for the pride it takes in the school, and also for contributing funds to construct the perimeter fence around the school.
    "We have a 10-foot-high block and steel fence around the nine and a half acres around the school. We have furniture here that we have contributed to other schools in the area. It's our school, and the community is as vigilant as we are about the school's property," said Morrison.
    Copeland said many, including ministry officials, expressed surprise that the project finished on time and on budget.
    "It takes management and dedication," he said simply.
    Meanwhile, over at Denbigh High School, principal Kasan Martin-Troupe said she could not give permission to the team to take pictures of the completed block without permission from the board.
    However, when The Sunday Gleaner visited the school last week, at least 10 completed rooms were observed serving as classrooms in the newest block.
    Martin-Troupe said she was unable to give any information on the project, saying it was completed before her time.
    However, our news team was told that the new two-storey block was completed on time and also within budget
    The same type of thinking that created a problem cannot be used to solve the problem.

    Comment


    • #3
      Originally posted by Time View Post
      Meanwhile, over at Denbigh High School, principal Kasan Martin-Troupe said she could not give permission to the team to take pictures of the completed block without permission from the board.
      Why not?!? KMT!


      BLACK LIVES MATTER

      Comment


      • #4
        Impressive!

        Comment


        • #5
          Originally posted by Mosiah View Post

          Any explanation of how the money was spent would have to come from the two contractors
          Really...so the contractor paid themselves?

          Comment


          • #6
            You do know that was the reporter's statement, right?


            BLACK LIVES MATTER

            Comment

            Working...
            X