by accident.. a Termite ridden hulk...
"Disbursement of the money was contingent on a number of conditions," said Blair.
"Altogether, it took six months initially and the project could have started in July 2010. Unfortunately, the first project coordinator selected moved on before starting the project. The project coordinator selection process had to be restarted, and hence the first disbursement took place in September 2010."
Accomplishments since July include selection of the 20 wind monitoring sites, verification of the methods of data collection with UWI and other experts, and publication of general procurement notices.
"We are now close to selecting the consultants and meeting our project timeline of an April 2011 start date," Blair said.
The project has a three-year timeline, which includes the study of a one-megawatt solar facility in Portmore, St Catherine.
The PCJ said last year that Jamaica was exploring 22 new wind-energy sites, to add wind-generated electricity to the existing Wigton I, and a US$49-million Wigton II in southern Manchester."
lol !! Dem waste 2 years suh ah man can eat a likke IDB food ?
5 years... and yuh can bet dem find a way to fvck it up..
The Intellectual Ghetto & Termite Co. strikes again.. meanwhile.. where is Professor Chen in this Anancy activity.. him wise to stay FAR !
http://jamaica-gleaner.com/gleaner/2...#disqus_thread
"Disbursement of the money was contingent on a number of conditions," said Blair.
"Altogether, it took six months initially and the project could have started in July 2010. Unfortunately, the first project coordinator selected moved on before starting the project. The project coordinator selection process had to be restarted, and hence the first disbursement took place in September 2010."
Accomplishments since July include selection of the 20 wind monitoring sites, verification of the methods of data collection with UWI and other experts, and publication of general procurement notices.
"We are now close to selecting the consultants and meeting our project timeline of an April 2011 start date," Blair said.
The project has a three-year timeline, which includes the study of a one-megawatt solar facility in Portmore, St Catherine.
The PCJ said last year that Jamaica was exploring 22 new wind-energy sites, to add wind-generated electricity to the existing Wigton I, and a US$49-million Wigton II in southern Manchester."
lol !! Dem waste 2 years suh ah man can eat a likke IDB food ?
5 years... and yuh can bet dem find a way to fvck it up..
The Intellectual Ghetto & Termite Co. strikes again.. meanwhile.. where is Professor Chen in this Anancy activity.. him wise to stay FAR !